LCC has been consulted on the Mayor's Cycle Superhighways proposals.
The findings are summarised as:
LCC’s Route Affirmation Process has led us to the conclusion that some of the proposed routes have such low potential as Cycle Superhighways that they should not go ahead.
A summary of the route affirmation findings shows that the appraised routes fall into three clusters.
Cluster One: Proceed to the next stage of a more detailed User Assessment
H8 (A3205-A3), H9 (A315), H2 (A11-A118), H1 (A10)
Cluster Two: Consider alternative alignments to part(s) of the route
H6 (A215-A2216), H4 (A200-A206), and H12 (A1)
Cluster Three: Do not proceed and identify alternative route with greater potential
H5 (A202-A20), H11 (A5), and H10 (A40-A219)
This accords with Brent Cyclists' opinion that both of the routes of immediate concern to our members, route 11 and route 10, are inadequate, and should not proceed as planned. We await a response from TfL and the Mayor